How a CAFM selection runs, and how long it takes
For a mid-sized portfolio, plan on four to five months from kick-off to contract, or six to nine where a tender committee is involved. If you are still choosing between a CAFM and a CMMS, start with how CAFM, CMMS and IWMS differ.
Weeks 1 to 3
Prepare
Agree the scope, the budget range and the final decision-maker, and collect volumes: buildings, assets, users and work orders a month.
Weeks 3 to 6
Requirements and long list
Edit the requirements, write your demo scenarios and use a short request for information (RFI) to reach five or six vendors.
Weeks 6 to 10
Issue the RFP
Send the workbook with a portfolio profile and a commercial template. Allow three to four weeks for responses.
Weeks 10 to 13
Evaluate and demo
Score the written responses, shortlist two or three vendors and run the scripted demos in the same week.
Weeks 13 to 16
References and final offers
Call references, visit a live site and ask for best and final offers.
Weeks 16 to 20
Award
Finish the IT and security review, negotiate and sign. Implementation takes four to eight weeks for one building with clean data, or three to six months for a portfolio that needs an asset survey.
For the long list, our comparison of CAFM software in the UAE covers ten platforms and where each one fits.
Who to involve
Selections go wrong when the people who will use the system first meet it at training. Put them on the panel, and give one person the final say.
- Head of FM or operations
- Owns the decision and the business case.
- Helpdesk, supervisors and technicians
- They use it every hour and notice a slow app in seconds.
- Finance
- Billing, cost centres, VAT and e-invoicing.
- Procurement
- The process, the evaluation rules and the contract terms.
- IT and information security
- Hosting, single sign-on, integrations and data residency.
- HSE or compliance
- Statutory maintenance and inspection evidence.
- Owner or provider side
- Asset and owners' association managers for owners; contract managers for FM providers.
Writing requirements a vendor can answer clearly
Each line should describe an outcome you can test, not a feature name. “The system has a mobile app” gets a yes from every vendor. “A technician can complete a PPM checklist with photos in a plant room with no signal, and it syncs later” separates them.
Keep one requirement per row so it can be scored on its own, and put the context (buildings, assets, daily users, systems to connect) in the RFP pack. Avoid words nobody can test, such as user-friendly.
Setting priorities with MoSCoW
MoSCoW sorts requirements into four groups. The workbook uses the first three; leave the fourth out of the RFP.
- Must
- You would reject a vendor that cannot meet it.
- Should
- Important and heavily weighted, but a gap can be worked around.
- Could
- Useful if it comes at little cost.
- Won't (this time)
- Parked for a later phase, so it does not dilute the scores.
If more than half the list is Must, it has not been prioritised. About four in ten of the template's rows are Must by default.
Demo scripts built from your own scenarios
A standard demo shows the product at its best; a scripted demo shows it doing your work. Send every shortlisted vendor the same scenarios and a sample of your data a week ahead, and run them in the same order.
The Demo script sheet has 12 scenarios, from an out-of-hours leak reported in Arabic to a month-end penalty calculation that tests whether your SLA rules match the contract. Ask for one live configuration change and use the app on a real phone in airplane mode. Evaluators score alone, then compare.
Scoring and weighting
The Scoring sheet works in three layers.
- Each requirement is scored 0 to 5 and multiplied by its priority: Must 3, Should 2, Could 1.
- Points are totalled by module and divided by the maximum, giving a module score.
- Module scores are multiplied by weights that total 100%, giving the technical score.
Price is scored separately: the lowest five-year cost scores 100%, and each other vendor scores the lowest cost divided by theirs. Many tenders in the region weight technical and commercial 70/30 or 60/40. Fix the weights before responses arrive, and treat a Must answered No as a decision: the vendor is out, or the requirement is downgraded for everyone.
Reference checks
Ask for three references of similar size and sector, one in your country, and call them without the vendor present.
- Did go-live happen on the planned date, and if not, why not?
- What still does not work the way the demo suggested?
- How quickly does support fix a critical issue at the weekend?
- What share of technicians use the mobile app every day?
- Would you choose the same system again?
Implementation and data migration questions
Disappointing CAFM projects usually go wrong in implementation, not selection. Get written answers before you sign.
- Who cleans the data, and who signs off each trial load?
- Which records are migrated (assets, open work orders, PPM schedules, history), and how many years?
- Who carries out the asset survey, and how is it priced?
- Which requirements need custom development rather than configuration?
- Who builds and maintains each integration, and at what annual cost?
- What happens to your configuration at each upgrade?
If your PPM programme will use SFG20 tasks, confirm whether the vendor includes SFG20 content or expects you to license it.
Total cost of ownership over five years
Licence price is the easiest number to compare and rarely the one that decides the cost. Ask every vendor to price five years on the same volumes, including:
- Subscription or licence, maintenance and the cap on annual increases
- Implementation, data migration, integrations and training
- Asset survey and tagging, often the largest single line in year one
- Hosting, extra storage and SMS or WhatsApp charges
- Mobile devices, tags and label printers
- Change requests and support beyond the included hours
- Your own staff time, and the cost of leaving
UAE and GCC requirements to include
Lists written for Europe or North America miss what causes trouble here. For a wider view, see facility management software in the UAE.
Arabic and bilingual reporting
Owners, government clients and tenants often need Arabic even when office users work in English. Ask for reports and portals in proper right-to-left Arabic, and a sample report.
UAE e-invoicing
Mandatory from 1 January 2027 for businesses with revenue of AED 50 million or more, 1 July 2027 for the rest and 1 October 2027 for government entities. The CAFM must feed invoice-ready data to your ERP or Accredited Service Provider. See what UAE e-invoicing means for CAFM and CMMS.
ZATCA FATOORA in Saudi Arabia
Saudi e-invoicing has applied since December 2021, with the integration phase rolling out in waves since January 2023. Confirm which system sends each Saudi entity's invoices.
Mollak for jointly owned property
Owners' associations in Dubai report service charges through Mollak, so CAFM cost allocation (common areas, reserve fund, recoverable costs) should follow your budget categories.
Dubai Municipality and Civil Defence evidence
Inspectors ask for maintenance history on fire and life safety systems, water tanks and pools. Ask each vendor for a 12-month evidence pack on one system in the demo.
Data residency and hosting
Government and government-related clients often require data to stay in the UAE or Saudi Arabia. Ask which provider and region host production data and backups.
Mobile use by multinational teams
Test the app in the languages your technicians read, such as Hindi, Urdu, Malayalam or Tagalog, offline and on a low-cost Android phone.
Working calendars
SLA clocks must follow each country's weekend, public holidays and Ramadan hours, and the UAE and Saudi weekends differ.
Common mistakes
- Starting from one vendor's brochure. Its feature names become your requirements, and the RFP is decided before it is issued.
- Marking everything Must. The scores can no longer tell the vendors apart.
- Leaving technicians out until training. Adoption is decided on the mobile app, by people the panel never asked.
- Underestimating the data. The asset survey and cleansing take longer than configuration, and decide whether people trust the system.
- Comparing licence prices. Implementation, integrations and the survey often cost more in year one than the software.
- Signing without exit terms. Data export and transition support are cheap to agree before signing and expensive afterwards.